Solvay Chemicals, Warrington – Case Study
JFHR was contracted for full demolition at Solvay’s Warrington Site, including the Boiler House and Turbine Hall to slab level.
JFHR was contracted for full demolition at Solvay’s Warrington Site, including the Boiler House and Turbine Hall to slab level.
JFHR was contracted to demolish the former Honey Monster factory, a 1930s concrete structure with 40 silos now serving as residential barges.
JFHR was contracted for the demolition of the former Sulzer Factory in Camp Hill, Birmingham, including slabs and contaminated hotspots.
Specialist groundworks supporting one of the UK’s largest transport infrastructure programmes.
The site was owned by the Royal Mail Group and used as one of the main sorting and distribution offices serving the West London area.
Devonport, the largest naval base in Western Europe, has supported the Royal Navy since 1691 and spans over 650 acres.
Historically, much of the 44 acre site was occupied by a foundry/iron works, evolving into an engineering works with chimneys, storage tanks, travelling cranes and...
John F Hunt Industrial undertook the role of Principal Contractor and Designer for the project at SGN Gaswoks, which involved the dismantling and demolition of...
Award winning £3.2m regeneration project encompassing demolition, remediation and formation of a new river channel, flood defence works, ecological formation and biodiversity enhancements
The project consisted of 33 acres split over 2 sites. The North site contained the former 1920’s Shredded Wheat Factory of which the original factory...
John F Hunt is contracted to strip out and remove assets from the historic Stag Brewery in Mortlake before its redevelopment.
JFHR was appointed by Essar Oil to deconstruct a corroded heat shield 100m up a live flare system at a Tier COMAH site.